# RUN REPORT: Rockport, Indiana to Evansville, step 3 engine (local OSM store, RoadAuthority, NLCD pavement, NHD and FRA crossings)

Run 2026-10-03T14:39:22.  Code `engine\` (`run_project.py rockport-evansville`), outputs `_Working\runs\rockport-evansville\`.  Total wall time 39.2 s before the screenshot.

## Rates in use: this project's overrides from the bid workbook

- Overrides file `engine\projects\rockport-evansville\assumptions_overrides.json`, existing file kept (pass --rebuild-overrides to regenerate from the bid).  Source: `BID CALC - HYPERLINK-ROCKPORT - QTS - ROCKPORT INDIANA - v2026.09.17.Final.xlsx`, sheet `CONSTRUCTION LABOR BID`, unit cost block (header row 257), segment 2 (column I: ROCKPORT, IN to EVANSVILLE).
- Base rate (bore class 2 dirt) $12.00 per ft (template default $12.00).  Rates the bid left blank fall back to the default multiple times this base: none.

| Rate | This project (bid) | Template default |
|:--|--:|--:|
| Bore class 1 | $12.00 | $12.00 |
| Bore class 2 | $12.00 | $12.00 |
| Bore class 3 | $12.00 | $12.00 |
| Bore class 4 | $16.00 | $20.00 |
| Bore class 5 | $25.00 | $30.00 |
| Bore class 6 | $35.00 | $45.00 |
| Bore class 7 | $45.00 | $60.00 |
| Bore class 8 | $100.00 | $200.00 |
| Bore class 9 | $175.00 | $450.00 |
| Trench class 1 | $5.00 | $5.50 |
| Trench class 2 | $5.00 | $5.50 |
| Trench class 3 | $6.00 | $10.00 |
| Trench class 4 | $10.00 | $15.00 |
| Trench class 5 | $12.00 | $20.00 |
| Trench class 6 | $16.00 | $25.00 |
| Trench class 7 | $22.00 | $35.00 |
| Crossing tier1 | $360.00 | $360.00 |
| Crossing tier2 | $150.00 | $175.00 |
| Crossing tier3 | $75.00 | $75.00 |

## A and Z

- Source: `Example - Rockport IN\QTS_Rockport Indiana.kmz`, KMZ line 'Rockpport to Evansville_SITCO' (3 lines in the file; selected by name); A = last vertex of the line as drawn.
- A (lon, lat) = (-87.032843, 37.944634) (A Rockport IN).  Z = (-87.521494, 38.019772) (Z Evansville).
- Human route length from the KMZ: 185,370 ft = 35.11 mi (541 vertices, geodesic).  Bid footage for this segment: 189,973 ft (`CONSTRUCTION LABOR BID!I94`).
- Snapped to graph nodes 181654754 (394 ft away) and 181947991 (310 ft away).

## Corridor graph (local Geofabrik store, no Overpass)

- bbox (left, bottom, right, top) = (-87.74159, 37.77072, -86.81275, 38.19369), pad 12 mi, network drive, source pickle cache of local Geofabrik store (osm_store.py).
- Store read: 44,880 ways from IN, KY in 0.71 s, 14,479 after de-duplication and the drive filter; graph build (chain merge on OSM node ids, split on highway, bridge, toll) 3.04 s: 167,703 segments and 161,120 nodes in the bbox to 20,797 nodes and 26,903 edges; **corridor total 3.9 s** (store timestamps {'IN': '2026-09-20T20:22:06Z', 'KY': '2026-09-20T20:22:06Z'}).
- Routing graph 20,576 nodes, 26,746 edges, 4,739 road miles; bridge edges 450, toll edges 0.

## Incorporated places

- `Places_Incorporated_2025` (EPSG:26914), 26 places in the bbox, read in 0.03 s: Boonville city, Chandler town, Chrisney town, Cynthiana town, Dale town, Darmstadt town, Elberfeld town, Evansville city, Fort Branch town, Gentryville town, Grandview town, Haubstadt town, Henderson city, Lewisport city, Lynnville town, Mackey town, Newburgh town, Owensboro city, Owensville town, Richland town, Rockport city, Santa Claus town, Tell City city, Tennyson town, Troy town, Whitesville city.
- 13,349 of 26,746 edges (25.6% of corridor footage) are inside a place (midpoint test, 0.57 s).  Top: Evansville city 3,719,506 ft, Henderson city 927,777 ft, Owensboro city 313,493 ft, Santa Claus town 268,102 ft, Boonville city 256,872 ft, Chandler town 186,119 ft.

## Soils

- 26,746 edges, 513,698 sample points every 50 ft, one window read of `CONUS_soilbid9_10m.tif` ([5410, 8450], 45.7 MB) in 0.05 s.  Corridor share by class: 1 0.7%, 2 52.3%, 3 4.2%, 4 3.6%, 5 35.4%, 6 1.0%, 7 1.9%, 11 0.5%, 12 0.3%.

## Pavement (new, Annual NLCD Fractional Impervious Surface 2025)

- `Annual_NLCD_FctImp_2025_CU_C1V2.tif`: 30 m percent impervious, window [1814, 2827] (5.1 MB) read in 0.02 s over the same 513,698 sample points; 0 nodata samples treated as 0 percent.
- The percent used is the mean of a 11 by 11 cell box (150 m each side of the sample, 0.04 s), not the cell under the road: the road's own cell reads 10 to 40 percent on any paved highway.  Corridor footage by bin, neighborhood: rural 52.9%, suburban 29.4%, urban 14.3%, dense 3.4%; by the raw centerline cell it would have been rural 12.5%, suburban 54.2%, urban 26.5%, dense 6.8%.  Edges whose neighborhood mean is 10 percent or more: 20,590 of 26,746 (centerline cell: 25,161).
- Used twice: the metro multiplier per edge is the footage-weighted mix of bin multipliers (rural 1.0, suburban 1.05, urban 1.2, dense 1.5, placeholders until step 4), and the not-bore rule now requires the edge mean under 10 percent.  Trench allowed on 51.4% of corridor footage under `place_pavement_soil`.

## Permitting authority (new, FiberBid RoadAuthority join)

- `RoadAuthority` bbox read: 32,065 HPMS 2024 segments in 11.87 s; classes {'state_dot': 17803, 'county': 7142, 'municipal': 6041, 'unknown': 557, 'private': 386, 'other_public': 131, 'federal_agency': 5}; confidence {'rule_verified': 30986, 'unknown': 557, 'inferred': 522}.
- Join: nearest segment within 30 m at 25, 50 and 75 percent of each edge; **24,130 of 26,746 edges matched, 92.1% of footage** (1.9 s).  Unmatched footage takes municipal inside a place, else county.
- Corridor footage by permit class: county 15,205,123 ft, municipal 5,616,533 ft, state_dot 3,145,513 ft, interstate 1,022,256 ft, federal_or_tribal 33,831 ft.
- Top authorities by footage: Spencer County 3,564,160 ft, Warrick County 3,544,527 ft, Evansville city 2,930,697 ft, Vanderburgh County 2,927,906 ft, VINCENNES 2,068,618 ft, Henderson County 918,020 ft, Daviess County 884,748 ft, Henderson city 649,820 ft.

## Crossings (new: NHD water, FRA rail, FEMA floodway, USACE navigable)

- NHD (IN, KY): 1,417 water polygons ({'LakePond': 1215, 'Reservoir': 165, 'StreamRiver': 37}) and 70,371 flowlines ({'intermittent': 24980, 'artificial path': 19049, 'canal/ditch': 16567, 'perennial': 9775}) in the bbox, read in 3.87 s.
- FRA grade crossings in the bbox: 578 ({'At Grade': 525, 'RR Under': 34, 'RR Over': 19}).  FEMA floodway polygons: 79 of 12,317 flood zone polygons.  USACE navigable waterway links: 9 (OHIO RIVER 6, GREEN RIVER 3).
- Detection on all 26,746 edges in 12.25 s: crossings by kind {'rail': 378, 'water': 859, 'dry_bridge': 206}; edges with a crossing 1,368; edges with only minor (intermittent, ephemeral, canal) flowline hits and no bridge, counted but not tiered: 3,957; floodway edges 688, navigable edges 23, rail-over-road flags 18.
- Rules (assumptions `crossings`): polygon water on the edge: length = intersection ft (a bridge edge uses at least its own length); else a bridge edge over any flowline: length = bridge edge length; else a perennial flowline with no bridge: no_bridge_perennial_ft; minor (intermittent, ephemeral, canal) flowlines with no bridge are counted and flagged, not tiered, unless tier_minor_without_bridge is true.  Rail: At Grade: rail crossing of at_grade_ft on the nearest edge within join_max_m; RR Under (road bridge over rail): rail crossing of rr_under_ft (the bore under the tracks and the embankment, not the whole bridge; a 776 ft overpass at FM 1788 near Midland priced as Tier 2 rail before this, 2026-09-21); RR Over (rail bridge over the road): flag only.  Forced Tier 1: a water crossing within navigable_within_m of the USACE navigable waterway network is Tier 1 at any length (the Corps Section 10 rule). A water crossing on an edge inside a FEMA floodway polygon is Tier 1 when it is a real crossing of the floodway stream: polygon water or a bridge, at least floodway_min_ft long. A culvert-class default crossing of a side creek inside a wide floodway keeps its own tier (Ohio River bottoms finding, 2026-09-21).
- Priced at a tier across the whole graph: {'tier3': 1218, 'tier1': 17, 'tier2': 10} by tier, {'rail': 378, 'water': 859, 'dry': 8} by kind.

## GeoTel carrier routes

- 17,085 features in the bbox in 0.11 s.  Named carriers found: AT&T, COGENT, CROWN CASTLE, MOX, UNITI, ZAYO; not present: LUMEN, VERIZON, FIBERLIGHT, ARELION, SEGRA.
- Corridor shared footage (within 250 ft of a named carrier): 5,435,578 ft (21.7%); by carrier AT&T 3,671,951 ft, UNITI 1,834,865 ft, ZAYO 896,397 ft, MOX 535,910 ft, COGENT 170,860 ft, CROWN CASTLE 124,800 ft.

## Timings (seconds)

| Step | Seconds |
|:--|--:|
| Assumptions build | 1.09 |
| Corridor total (store read plus graph build, or pickle load) | 0.44 |
| Places total | 0.62 |
| Soils total | 0.75 |
| Pavement total | 0.41 |
| Road authority total | 13.86 |
| Crossings total | 17.38 |
| Carriers total | 3.06 |
| Pricing | 0.24 |
| Spread (all solves and bookkeeping) | 0.64 |
| Dijkstra solves only | 0.621 |
| Route diversity | 0.014 |
| Shared segments | 0.07 |
| Comparison (human route) | 0.25 |
| Outputs (KMZ, HTML) | 0.29 |
| Total before the screenshot | 39.2 |

## Kept routes

Spread settings: penalty 1.3, overlap max 0.7, detour cap 1.35 times the shortest kept, max 20 routes, max 60 iterations.  22 solves, 20 kept, 0 pruned by the final cap.  R01 is the cheapest kept route.  Dollars are at this project's rates.

| Route | Miles | Dollars | $/ft | Diversity % | Shared ft | Longest shared run ft | Carriers (ft within 250 ft) | Crossing $ | Tiered crossings (water, rail, dry) | Tier 1 | Worst crossing | Permit $ | Trench ft | Bore ft | Metro ft | Inside place ft | county ft | state_dot ft | municipal ft | interstate ft | Overlap vs R01 | residential mi | tertiary mi | trunk mi | unclassified mi | primary mi | secondary mi | motorway mi |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| R01 | 32.39 | $1,775,004 | 10.38 | 80.2% | 33,927 | 14,932 | AT&T 27,707; UNITI 10,413; ZAYO 5,588; MOX 484; CROWN CASTLE 285 | $101,361 | 13 (12, 1, 0) | 0 | Tier 3 water 360 ft Pigeon Creek; StreamRiver on Lynch Road $26,978 | $20,730 | 112,215 | 58,811 | 91,070 | 18,269 | 148,552 | 0 | 22,234 | 240 | 100.0% | 4.0 | 18.8 | 0.0 | 5.7 | 3.9 | 0.0 | 0.0 |
| R02 | 35.02 | $1,739,387 | 9.41 | 49.4% | 93,622 | 27,663 | AT&T 55,803; ZAYO 44,883; UNITI 26,362; MOX 559; CROWN CASTLE 189 | $145,656 | 15 (13, 2, 0) | 0 | Tier 3 water 360 ft Pigeon Creek; StreamRiver on Lynch Road $26,978 | $29,189 | 123,449 | 61,443 | 92,301 | 25,826 | 149,539 | 5,322 | 29,762 | 269 | 8.4% | 18.8 | 9.7 | 0.0 | 2.0 | 3.0 | 1.5 | 0.0 |
| R03 | 33.71 | $1,897,630 | 10.66 | 84.9% | 26,894 | 12,422 | AT&T 19,101; UNITI 11,668; ZAYO 4,479; MOX 519; CROWN CASTLE 189 | $123,861 | 16 (13, 3, 0) | 0 | Tier 3 water 360 ft Pigeon Creek; StreamRiver on Lynch Road $26,978 | $21,023 | 117,251 | 60,736 | 105,882 | 18,213 | 155,085 | 483 | 22,084 | 334 | 25.3% | 4.4 | 21.3 | 0.0 | 4.0 | 4.0 | 0.0 | 0.0 |
| R04 | 34.76 | $2,028,844 | 11.05 | 57.9% | 77,215 | 31,018 | UNITI 61,625; AT&T 50,279; CROWN CASTLE 7,490; ZAYO 7,139; MOX 512 | $165,000 | 14 (12, 2, 0) | 0 | Tier 3 water 482 ft Little Pigeon Creek; StreamRiver on SR 66 $36,153 | $48,739 | 78,474 | 105,079 | 126,440 | 56,171 | 117,409 | 17,983 | 48,160 | 0 | 3.0% | 14.7 | 1.9 | 7.2 | 2.1 | 1.5 | 7.5 | 0.0 |
| R05 | 35.60 | $2,007,772 | 10.68 | 60.0% | 75,131 | 15,620 | AT&T 36,296; UNITI 29,991; ZAYO 20,127; CROWN CASTLE 6,547; MOX 533 | $148,322 | 13 (10, 3, 0) | 0 | Tier 3 water 479 ft Little Pigeon Creek; StreamRiver on SR 66 $35,946 | $46,325 | 103,648 | 84,300 | 110,464 | 27,421 | 118,554 | 38,092 | 28,100 | 3,202 | 8.7% | 12.5 | 9.0 | 8.4 | 3.3 | 2.3 | 0.1 | 0.0 |
| R06 | 36.63 | $1,973,926 | 10.21 | 67.9% | 62,007 | 16,514 | ZAYO 22,660; AT&T 21,887; UNITI 19,936; MOX 14,561; CROWN CASTLE 285 | $172,945 | 18 (16, 2, 0) | 0 | Tier 3 water 360 ft Pigeon Creek; StreamRiver on Lynch Road $26,978 | $63,927 | 118,683 | 74,717 | 94,775 | 26,016 | 160,600 | 1,550 | 14,423 | 16,827 | 10.5% | 22.3 | 6.8 | 1.3 | 1.1 | 2.2 | 0.0 | 3.0 |
| R07 | 36.43 | $2,043,962 | 10.63 | 72.2% | 53,465 | 21,561 | AT&T 39,249; ZAYO 29,924; UNITI 7,169; CROWN CASTLE 2,910; MOX 538 | $163,921 | 18 (15, 3, 0) | 0 | Tier 3 water 269 ft Pigeon Creek; StreamRiver on Oak Hill Road $20,176 | $31,380 | 117,098 | 75,235 | 90,974 | 45,159 | 141,842 | 25,145 | 24,859 | 488 | 2.8% | 18.8 | 5.2 | 7.9 | 2.4 | 0.9 | 1.2 | 0.0 |
| R08 | 37.08 | $2,102,025 | 10.74 | 74.8% | 49,284 | 38,078 | ZAYO 45,686; UNITI 35,835; AT&T 35,781; MOX 496 | $134,084 | 16 (12, 4, 0) | 0 | Tier 3 water 398 ft Pigeon Creek; StreamRiver on North Green River Road $29,830 | $6,670 | 136,000 | 59,756 | 117,628 | 13,173 | 188,345 | 0 | 7,411 | 0 | 40.6% | 9.6 | 20.8 | 0.0 | 4.0 | 0.4 | 2.2 | 0.0 |
| R09 | 37.53 | $2,210,379 | 11.15 | 70.5% | 58,445 | 21,561 | AT&T 42,821; ZAYO 30,940; UNITI 14,660; CROWN CASTLE 3,650; MOX 533 | $156,421 | 17 (15, 2, 0) | 0 | Tier 3 water 269 ft Pigeon Creek; StreamRiver on Oak Hill Road $20,176 | $60,758 | 114,673 | 83,503 | 96,415 | 52,739 | 139,428 | 11,227 | 40,558 | 6,963 | 15.5% | 14.9 | 7.7 | 7.1 | 4.0 | 1.6 | 1.6 | 0.7 |
| R10 | 37.54 | $2,287,697 | 11.54 | 69.3% | 60,848 | 42,763 | AT&T 53,061; ZAYO 49,657; UNITI 40,844; MOX 496 | $145,294 | 14 (11, 3, 0) | 0 | Tier 3 water 398 ft Pigeon Creek; StreamRiver on North Green River Road $29,830 | $17,414 | 145,202 | 53,021 | 99,950 | 23,702 | 166,710 | 18,247 | 13,267 | 0 | 1.5% | 14.1 | 11.0 | 0.0 | 7.1 | 2.4 | 2.9 | 0.0 |
| R11 | 36.27 | $2,594,537 | 13.55 | 82.8% | 33,018 | 11,079 | UNITI 21,143; AT&T 19,275; ZAYO 15,783; MOX 484; CROWN CASTLE 189 | $138,150 | 13 (8, 5, 0) | 0 | Tier 3 water 360 ft Pigeon Creek; StreamRiver on Lynch Road $26,978 | $36,671 | 110,482 | 81,046 | 113,543 | 43,024 | 130,140 | 32,009 | 29,080 | 299 | 15.4% | 12.7 | 7.6 | 0.0 | 5.0 | 8.1 | 2.9 | 0.0 |
| R12 | 38.96 | $2,438,122 | 11.85 | 42.7% | 117,794 | 53,123 | UNITI 94,517; ZAYO 66,525; AT&T 61,147; COGENT 2,990; CROWN CASTLE 2,496; MOX 485 | $165,580 | 18 (13, 5, 0) | 0 | Tier 3 water 352 ft Cypress Creek; StreamRiver on SR 66 $26,408 | $72,362 | 68,982 | 136,747 | 176,484 | 60,902 | 60,651 | 97,014 | 48,064 | 0 | 2.4% | 6.0 | 8.1 | 21.1 | 0.9 | 0.6 | 2.4 | 0.0 |
| R13 | 37.53 | $2,609,621 | 13.17 | 79.9% | 39,835 | 10,965 | AT&T 23,252; ZAYO 18,973; UNITI 8,428; MOX 550 | $150,223 | 12 (8, 4, 0) | 0 | Tier 3 water 424 ft Bluegrass Creek on Heckel Road $31,812 | $25,963 | 128,543 | 69,594 | 100,147 | 38,844 | 143,608 | 38,523 | 16,007 | 0 | 1.5% | 13.8 | 10.4 | 0.0 | 6.0 | 4.9 | 2.4 | 0.0 |
| R14 | 40.36 | $2,405,248 | 11.29 | 69.0% | 66,105 | 17,803 | AT&T 40,944; UNITI 33,745; ZAYO 17,794; CROWN CASTLE 9,405; COGENT 8,958; MOX 559 | $147,120 | 20 (14, 6, 0) | 0 | Tier 3 water 255 ft Pigeon Creek; StreamRiver on trunk $19,129 | $37,355 | 114,580 | 98,497 | 127,780 | 51,096 | 150,414 | 32,676 | 29,718 | 269 | 8.6% | 12.0 | 16.7 | 3.3 | 3.8 | 4.3 | 0.1 | 0.0 |
| R15 | 42.92 | $2,269,853 | 10.02 | 51.2% | 110,572 | 33,526 | AT&T 79,397; UNITI 49,451; ZAYO 11,910; CROWN CASTLE 10,546; MOX 538 | $120,456 | 14 (14, 0, 0) | 0 | Tier 3 water 269 ft Pigeon Creek; StreamRiver on Oak Hill Road $20,176 | $42,620 | 113,995 | 112,640 | 144,781 | 47,651 | 155,407 | 37,518 | 33,223 | 488 | 0.3% | 14.5 | 11.5 | 4.7 | 7.0 | 2.8 | 2.4 | 0.0 |
| R16 | 41.98 | $2,634,111 | 11.88 | 56.2% | 97,166 | 36,753 | AT&T 64,368; UNITI 62,956; ZAYO 11,207; COGENT 3,396; CROWN CASTLE 2,917; MOX 512 | $186,106 | 15 (11, 4, 0) | 0 | Tier 3 water 482 ft Little Pigeon Creek; StreamRiver on SR 66 $36,153 | $72,115 | 80,050 | 141,597 | 163,764 | 73,671 | 114,522 | 40,494 | 66,630 | 0 | 0.3% | 10.2 | 5.3 | 11.7 | 5.3 | 1.1 | 8.4 | 0.0 |
| R17 | 43.42 | $2,540,559 | 11.08 | 79.8% | 46,412 | 21,911 | AT&T 40,104; ZAYO 8,180; UNITI 7,675; MOX 550 | $192,651 | 24 (19, 5, 0) | 0 | Tier 3 water 158 ft Pigeon Creek; StreamRiver on New Harmony Road $11,865 | $18,812 | 188,246 | 41,018 | 84,101 | 18,156 | 202,870 | 8,238 | 18,156 | 0 | 7.8% | 13.8 | 14.5 | 0.0 | 13.6 | 1.1 | 0.5 | 0.0 |
| R18 | 42.38 | $2,791,182 | 12.47 | 26.0% | 165,679 | 58,767 | UNITI 130,816; AT&T 84,555; ZAYO 65,660; COGENT 8,248; CROWN CASTLE 728; MOX 485 | $201,951 | 20 (15, 5, 0) | 0 | Tier 3 water 479 ft Little Pigeon Creek; StreamRiver on SR 66 $35,946 | $78,974 | 69,858 | 153,893 | 203,023 | 67,977 | 70,745 | 113,445 | 35,114 | 4,446 | 0.4% | 5.5 | 10.4 | 22.0 | 1.2 | 0.0 | 2.5 | 0.8 |
| R19 | 43.54 | $2,745,078 | 11.94 | 75.0% | 57,391 | 13,859 | AT&T 48,021; ZAYO 12,249; UNITI 3,099; MOX 1,680 | $142,371 | 13 (10, 3, 0) | 0 | Tier 3 water 424 ft Bluegrass Creek on Heckel Road $31,812 | $24,884 | 177,475 | 52,412 | 114,009 | 27,470 | 191,020 | 16,825 | 22,040 | 0 | 1.3% | 23.3 | 9.9 | 0.0 | 7.1 | 0.0 | 3.2 | 0.0 |
| R20 | 43.55 | $3,166,422 | 13.77 | 50.7% | 113,458 | 43,518 | AT&T 105,452; ZAYO 43,825; UNITI 39,112; MOX 496 | $153,139 | 16 (12, 4, 0) | 0 | Tier 3 water 398 ft Pigeon Creek; StreamRiver on North Green River Road $29,830 | $37,406 | 136,680 | 93,276 | 134,276 | 57,817 | 152,040 | 54,529 | 23,386 | 0 | 0.3% | 22.4 | 4.3 | 0.0 | 4.7 | 5.4 | 6.9 | 0.0 |

Soil footage per kept route (ft):

| Route | Soil 1 | Soil 2 | Soil 3 | Soil 4 | Soil 5 | Soil 6 | Soil 7 | Soil 10 | Soil 11 | Flagged ft |
|---|---|---|---|---|---|---|---|---|---|---|
| R01 | 1,875 | 101,526 | 23,990 | 18,031 | 25,207 | 0 | 0 | 397 | 0 | 346 |
| R02 | 1,595 | 144,754 | 19,358 | 10,385 | 5,611 | 2,940 | 150 | 97 | 0 | 0 |
| R03 | 198 | 107,252 | 19,051 | 20,834 | 30,256 | 297 | 0 | 98 | 0 | 48 |
| R04 | 1,447 | 166,503 | 8,341 | 543 | 4,046 | 1,170 | 299 | 141 | 1,062 | 1,022 |
| R05 | 1,447 | 157,584 | 13,226 | 6,903 | 7,759 | 635 | 346 | 48 | 0 | 0 |
| R06 | 1,595 | 158,027 | 16,850 | 6,370 | 7,371 | 2,940 | 150 | 97 | 0 | 0 |
| R07 | 1,447 | 140,853 | 25,760 | 11,942 | 9,774 | 1,143 | 789 | 142 | 482 | 482 |
| R08 | 544 | 92,300 | 38,266 | 23,203 | 40,601 | 0 | 446 | 397 | 0 | 346 |
| R09 | 802 | 141,342 | 25,542 | 11,942 | 16,141 | 1,143 | 789 | 142 | 333 | 333 |
| R10 | 198 | 85,071 | 29,127 | 8,105 | 74,927 | 350 | 349 | 97 | 0 | 0 |
| R11 | 248 | 87,821 | 18,184 | 2,432 | 82,299 | 0 | 446 | 97 | 0 | 0 |
| R12 | 6,079 | 185,258 | 9,911 | 0 | 2,857 | 1,279 | 0 | 146 | 198 | 240 |
| R13 | 198 | 84,883 | 24,035 | 683 | 88,105 | 136 | 0 | 97 | 0 | 0 |
| R14 | 8,293 | 118,940 | 33,951 | 26,183 | 23,857 | 297 | 0 | 141 | 1,415 | 1,462 |
| R15 | 300 | 215,216 | 8,149 | 0 | 1,458 | 598 | 143 | 95 | 678 | 725 |
| R16 | 300 | 201,009 | 9,888 | 543 | 6,849 | 1,170 | 299 | 146 | 1,442 | 1,442 |
| R17 | 802 | 66,550 | 38,804 | 42,490 | 78,991 | 246 | 0 | 735 | 647 | 1,343 |
| R18 | 1,984 | 199,327 | 13,410 | 643 | 6,346 | 859 | 488 | 144 | 549 | 534 |
| R19 | 3,680 | 70,285 | 31,787 | 18,157 | 104,048 | 1,343 | 548 | 39 | 0 | 0 |
| R20 | 3,530 | 76,604 | 49,503 | 0 | 98,523 | 1,383 | 298 | 114 | 0 | 0 |

Every crossing priced at a tier on the cheapest route (R01):

| Tier | Kind | Name | Road | Length ft | Dollars | Forced Tier 1 | Detection |
|:--|:--|:--|:--|--:|--:|:--|:--|
| tier3 | water | Pigeon Creek; StreamRiver | Lynch Road | 360 | $26,978 |  | NHD polygon intersection (bridge length used, longer) |
| tier3 | water | perennial | residential | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Honey Creek | East County Road 350 North | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | County Road 75 East | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | East County Road 400 North | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Caney Creek | East Myers Road | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | rail | NS railroad at ROEDER ROAD (FRA 858663E) | West Roeder Road | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | water | Mitchem Ditch | Oak Grove Road | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | Telephone Road | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Cypress Creek | West Roeder Road | 91 | $6,829 |  | bridge edge over an NHD flowline |
| tier3 | water | Little Pigeon Creek; StreamRiver | South Bullocktown Road | 50 | $3,723 |  | NHD polygon intersection |
| tier3 | water | StreamRiver | North County Road 900 West | 35 | $2,647 |  | NHD polygon intersection |
| tier3 | water | StreamRiver | South Bullocktown Road | 16 | $1,183 |  | NHD polygon intersection |

Solve log (every iteration):

| Iter | Solve s | Miles | Dollars | Max overlap vs kept | Result |
|--:|--:|--:|--:|--:|:--|
| 1 | 0.015 | 32.39 | $1,775,004 | 0.0% | kept |
| 2 | 0.013 | 35.02 | $1,739,387 | 8.4% | kept |
| 3 | 0.013 | 34.76 | $2,028,844 | 5.1% | kept |
| 4 | 0.013 | 33.71 | $1,897,630 | 25.3% | kept |
| 5 | 0.014 | 36.43 | $2,043,962 | 17.7% | kept |
| 6 | 0.014 | 37.54 | $2,287,697 | 13.4% | kept |
| 7 | 0.015 | 38.96 | $2,438,122 | 6.5% | kept |
| 8 | 0.014 | 37.53 | $2,609,621 | 15.1% | kept |
| 9 | 0.015 | 35.6 | $2,007,772 | 25.5% | kept |
| 10 | 0.016 | 42.92 | $2,269,853 | 12.9% | kept |
| 11 | 0.106 | 43.42 | $2,540,559 | 7.8% | kept |
| 12 | 0.026 | 37.08 | $2,102,025 | 40.6% | kept |
| 13 | 0.022 | 36.63 | $1,973,926 | 45.0% | kept |
| 14 | 0.019 | 43.54 | $2,745,078 | 18.7% | kept |
| 15 | 0.023 | 41.98 | $2,634,111 | 24.2% | kept |
| 16 | 0.038 | 40.36 | $2,405,248 | 30.4% | kept |
| 17 | 0.034 | 48.83 | $2,881,148 | 9.5% | detour cap |
| 18 | 0.023 | 37.53 | $2,210,379 | 52.4% | kept |
| 19 | 0.021 | 36.27 | $2,594,537 | 29.4% | kept |
| 20 | 0.021 | 42.38 | $2,791,182 | 35.3% | kept |
| 21 | 0.117 | 50.16 | $2,804,864 | 23.5% | detour cap |
| 22 | 0.029 | 43.55 | $3,166,422 | 28.3% | kept |

## Comparison only, never a target: the human route and the bid, like for like

- The KMZ line was sampled every 50 ft (3,708 samples) for soils, places, pavement and the nearest HPMS segment; each sample took the OSM class and toll flag of the nearest corridor-graph sample point within 30 m (96.4% matched; the rest priced as unclassified county road).  Crossings on the human route are those of the 104 graph edges it runs along (181,069 ft of edges; an edge counts when at least 2 samples and 30 percent of its own sample count land on it).
- Inside-place footage 16,597 ft (Evansville city 16,597 ft); metro footage (pavement 10 percent or more) 60,790 ft; mean neighborhood pavement 12.2 percent (centerline cell 26.7); permit class footage county 164,473 ft, municipal 19,247 ft, interstate 1,350 ft, state_dot 300 ft.
- **Tool price of the human route at the bid's own rates: $1,832,666** (9.89 per ft): soil $1,698,568, crossings $112,637 (14 tiered: {'water': 11, 'rail': 3}, {'tier3': 14}), permitting adder $21,461; bore 62,090 ft, trench 123,280 ft.  At template defaults (base $12.00): $2,116,380.
- **Bid underground construction lines (footage times unit cost, `CONSTRUCTION LABOR BID` rows under the footage and unit cost headers, segment column I): $1,631,959 for 189,973 ft.**  trench 134,808 ft $853,074; bore 54,215 ft $707,636; crossing 950 ft $71,250.
- Plow convention: the tool prices every not-bore foot at the trench rate (Jeff, 2026-09-21).  The bid's plow lines repriced at this project's trench rates add $0, so the bid's own footage at the tool's convention is $1,631,959.
- **Ratios: tool over bid comparable 1.123; tool over bid-at-tool-convention 1.123; tool over construction labor K 0.488; tool over bid total P 0.248.**  Within 10 percent of the comparable underground number: no.  Footage: tool bore 62,090 ft (bid bore plus tiered crossings 55,165 ft), tool not-bore 123,280 ft (bid plow plus trench 134,808 ft); tool tiered crossing footage 1,502 ft $112,637 versus the bid's crossing lines $71,250.
- Bid presentation for this segment (row 10, SEGMENT 2: ROCKPORT, IN - EVANSVILLE): LF 189,973, construction labor K $3,753,866, materials O $3,391,572, total P $7,392,403.  Construction labor also holds handholes, splicing, restoration, traffic control and the like, which the tool does not price.
- **Human route diversity: 75.1%**; shared 46,192 ft, near band 11,048 ft, longest continuous shared run 22,696 ft, most carriers on one stretch 3; by carrier AT&T 39,244 ft, UNITI 10,548 ft, ZAYO 4,949 ft, MOX 1,550 ft, CROWN CASTLE 250 ft.
- Cheapest tool route R01 versus the human route: 32.39 mi versus 35.11 mi (ratio 0.923); $1,775,004 versus $1,832,666 by the same model and rates (ratio 0.969); diversity 80.2% versus 75.1%.

| Soil class | Tool sample of the human line (ft) | Bid calculator soils block (ft) |
|--:|--:|--:|
| 1 | 2,850 | 0 |
| 2 | 127,129 | 132,368 |
| 3 | 19,347 | 19,455 |
| 4 | 17,947 | 17,530 |
| 5 | 17,397 | 16,712 |
| 6 | 300 | 300 |
| 10 | 400 | 493 |
| 11 | 0 | 3,022 |
| 12 | 0 | 93 |

Tiered crossings on the human route (from the graph edges it runs along):

| Tier | Kind | Name | Road | Length ft | Dollars | Forced Tier 1 |
|:--|:--|:--|:--|--:|--:|:--|
| tier3 | water | Pigeon Creek; StreamRiver | Lynch Road | 360 | $26,978 |  |
| tier3 | water | Honey Creek | East County Road 350 North | 100 | $7,500 |  |
| tier3 | rail | NS railroad at ROAD 350 NORTH (FRA 735852K) | East County Road 350 North | 100 | $7,500 |  |
| tier3 | water | perennial | West County Road 200 North | 100 | $7,500 |  |
| tier3 | water | Huffman Ditch | West County Road 200 North | 100 | $7,500 |  |
| tier3 | water | Robert Richard Drain | North 800 West | 100 | $7,500 |  |
| tier3 | water | Hooppole Ditch | North County Road 850 West | 100 | $7,500 |  |
| tier3 | water | Caney Creek | East New Hope Road | 100 | $7,500 |  |
| tier3 | rail | NS railroad at ROEDER ROAD (FRA 858663E) | West Roeder Road | 100 | $7,500 |  |
| tier3 | water | Mitchem Ditch | Oak Grove Road | 100 | $7,500 |  |
| tier3 | rail | NS railroad at EPWORTH ROAD (FRA 719906X) | Epworth Road | 100 | $7,500 |  |
| tier3 | water | Cypress Creek | West Roeder Road | 91 | $6,829 |  |
| tier3 | water | StreamRiver | North County Road 900 West | 35 | $2,647 |  |
| tier3 | water | StreamRiver | South Bullocktown Road | 16 | $1,183 |  |

## Still placeholder (all marked in assumptions_defaults.json)

- Metro multipliers (1.0, 1.15, 1.4, 2.0 by pavement bin) and permitting adders (county 0, state DOT 0.05, municipal 0.15, interstate 0.5, toll 0.75, federal or tribal 0.5, in multiples of dirt bore per foot) are Claude's placeholders until step 4 calibration.  The data behind them is now real.
- Crossing default lengths (perennial flowline with no bridge 100 ft, FRA at-grade rail 100 ft) and the rule that minor flowlines without a bridge are not tiered are Claude's interim choices; the tier rates and the calculator's three tiers are Jeff's.
- Soil classes 10, 11, 12 are priced as class 3 and their footage is reported as flagged.  Plow rows are unused; not-bore uses the trench multiples.
- Pipeline crossings (Big Springs priced 67,000 ft of them) have no data layer in the tool.

## What failed or was not checked

- Nothing failed in the run that produced this report (the report is written only after every step returned).
- Not checked: GeoTel positional accuracy; OSM bridge edges spanning the whole physical bridge; whether every FRA crossing sits within 30 m of its OSM road.
- The inside-place test uses the edge midpoint; the RoadAuthority join votes over three points per edge; the human line is tested per sample.
- The human route's crossings are taken from the graph edges it runs along, so a crossing on an edge the snap did not claim is missed, and its crossing footage is also priced once more as soil footage (small: 1,502 ft).

## Files

- `_Working\runs\rockport-evansville\routes.kmz`: one folder per kept route, A, Z, the human route (comparison only), shared segments, and tiered crossing points.
- `_Working\runs\rockport-evansville\explorer.html`: Leaflet map (routes, human route, shared segments, crossings), scatter, sortable table with permit and crossing columns, assumptions panel.  Needs internet for tiles and Leaflet.
- `_Working\runs\rockport-evansville\results.json`: every number in this report.  `bid_extract.json`: every bid line read, with cell addresses.  `run.log`: console log.
- `engine\projects\rockport-evansville\project.json` and `assumptions_overrides.json`.

- `_Working\runs\rockport-evansville\explorer-screenshot.png`: screenshot written (750,414 bytes) in 1.0 s; chrome exit 0.