# RUN REPORT: Rockport, Indiana to Nashville, step 3 engine (local OSM store, RoadAuthority, NLCD pavement, NHD and FRA crossings)

Run 2026-10-03T14:43:23.  Code `engine\` (`run_project.py rockport-nashville`), outputs `_Working\runs\rockport-nashville\`.  Total wall time 98.43 s before the screenshot.

## Rates in use: this project's overrides from the bid workbook

- Overrides file `engine\projects\rockport-nashville\assumptions_overrides.json`, existing file kept (pass --rebuild-overrides to regenerate from the bid).  Source: `BID CALC - HYPERLINK-ROCKPORT - QTS - ROCKPORT INDIANA - v2026.09.17.Final.xlsx`, sheet `CONSTRUCTION LABOR BID`, unit cost block (header row 257), segment 1 (column H: ROCKPORT, IN to NASHVILLE).
- Base rate (bore class 2 dirt) $12.00 per ft (template default $12.00).  Rates the bid left blank fall back to the default multiple times this base: none.

| Rate | This project (bid) | Template default |
|:--|--:|--:|
| Bore class 1 | $12.00 | $12.00 |
| Bore class 2 | $12.00 | $12.00 |
| Bore class 3 | $12.00 | $12.00 |
| Bore class 4 | $16.00 | $20.00 |
| Bore class 5 | $25.00 | $30.00 |
| Bore class 6 | $35.00 | $45.00 |
| Bore class 7 | $45.00 | $60.00 |
| Bore class 8 | $100.00 | $200.00 |
| Bore class 9 | $175.00 | $450.00 |
| Trench class 1 | $5.00 | $5.50 |
| Trench class 2 | $5.00 | $5.50 |
| Trench class 3 | $6.00 | $10.00 |
| Trench class 4 | $10.00 | $15.00 |
| Trench class 5 | $12.00 | $20.00 |
| Trench class 6 | $16.00 | $25.00 |
| Trench class 7 | $22.00 | $35.00 |
| Crossing tier1 | $360.00 | $360.00 |
| Crossing tier2 | $150.00 | $175.00 |
| Crossing tier3 | $75.00 | $75.00 |

## A and Z

- Source: `Example - Rockport IN\QTS_Rockport Indiana.kmz`, KMZ line 'Rockport to Nashville' (3 lines in the file; selected by name); A = first vertex of the line as drawn.
- A (lon, lat) = (-87.036655, 37.934953) (A Rockport IN).  Z = (-86.782559, 36.155146) (Z Nashville).
- Human route length from the KMZ: 790,485 ft = 149.71 mi (4289 vertices, geodesic).  Bid footage for this segment: 800,633 ft (`CONSTRUCTION LABOR BID!H94`).
- Snapped to graph nodes 502845052 (1305 ft away) and 202328837 (159 ft away).

## Corridor graph (local Geofabrik store, no Overpass)

- bbox (left, bottom, right, top) = (-87.25400, 35.98123, -86.56521, 38.10887), pad 12 mi, network drive, source pickle cache of local Geofabrik store (osm_store.py).
- Store read: 169,090 ways from IN, KY, TN in 17.37 s, 47,776 after de-duplication and the drive filter; graph build (chain merge on OSM node ids, split on highway, bridge, toll) 20.96 s: 706,508 segments and 689,106 nodes in the bbox to 64,841 nodes and 80,587 edges; **corridor total 40.82 s** (store timestamps {'IN': '2026-09-20T20:22:06Z', 'KY': '2026-09-20T20:22:06Z', 'TN': '2026-09-20T20:22:06Z'}).
- Routing graph 64,110 nodes, 80,063 edges, 15,465 road miles; bridge edges 1635, toll edges 0.

## Incorporated places

- `Places_Incorporated_2025` (EPSG:26914), 91 places in the bbox, read in 0.03 s: Adairville city, Adams city, Ashland City town, Auburn city, Beaver Dam city, Belle Meade city, Berry Hill city, Boonville city, Bowling Green city, Bremen city, Brentwood city, Burns town, Calhoun city, Caneyville city, Cannelton city, Cedar Hill city, Centertown city, Central City city, Charlotte town, Chrisney town, Clarksville city, Cloverport city, Coopertown town, Cross Plains city, Dickson city, Drakesboro city, Elkton city, Fairview city, Fordsville city, Forest Hills city, Franklin city, Franklin city, Gallatin city, Gentryville town, Goodlettsville city, Grandview town, Greenbrier town, Greenville city, Guthrie city, Hardinsburg city, Hartford city, Hawesville city, Hendersonville city, Hopkinsville city, Irvington city, Island city, Kingston Springs town, La Vergne city, Leitchfield city, Lewisburg city, Lewisport city, Livermore city, McHenry city, Millersville city, Mitchellville city, Morgantown city, Mount Juliet city, Nashville-Davidson metropolitan government (balance), Nolensville town, Oak Grove city, Oak Hill city, Orlinda city, Owensboro city, Pegram town, Pembroke city, Pleasant View city, Portland city, Powderly city, Richland town, Ridgetop city, Rochester city, Rockport city, Rockport city, Russellville city, Sacramento city, Santa Claus town, Slayden town, Smyrna town, South Carrollton city, Springfield city, Tell City city, Tennyson town, Trenton city, Troy town, Vanleer town, White Bluff town, White House city, White Plains city, Whitesville city, Woodburn city, Woodbury city.
- 54,536 of 80,063 edges (39.6% of corridor footage) are inside a place (midpoint test, 2.11 s).  Top: Nashville-Davidson metropolitan government (balance) 17,860,077 ft, Owensboro city 1,674,429 ft, Hendersonville city 1,554,987 ft, Brentwood city 1,113,726 ft, Springfield city 642,811 ft, Goodlettsville city 641,597 ft.

## Soils

- 80,063 edges, 1,673,068 sample points every 50 ft, one window read of `CONUS_soilbid9_10m.tif` ([24288, 8284], 201.2 MB) in 0.31 s.  Corridor share by class: 1 0.3%, 2 36.0%, 3 14.1%, 4 2.7%, 5 20.3%, 6 5.1%, 7 20.7%, 9 0.3%, 10 0.1%, 12 0.4%.

## Pavement (new, Annual NLCD Fractional Impervious Surface 2025)

- `Annual_NLCD_FctImp_2025_CU_C1V2.tif`: 30 m percent impervious, window [8107, 2772] (22.5 MB) read in 0.05 s over the same 1,673,068 sample points; 0 nodata samples treated as 0 percent.
- The percent used is the mean of a 11 by 11 cell box (150 m each side of the sample, 0.16 s), not the cell under the road: the road's own cell reads 10 to 40 percent on any paved highway.  Corridor footage by bin, neighborhood: rural 57.3%, suburban 30.2%, urban 10.8%, dense 1.7%; by the raw centerline cell it would have been rural 22.2%, suburban 51.4%, urban 21.2%, dense 5.2%.  Edges whose neighborhood mean is 10 percent or more: 58,944 of 80,063 (centerline cell: 72,379).
- Used twice: the metro multiplier per edge is the footage-weighted mix of bin multipliers (rural 1.0, suburban 1.05, urban 1.2, dense 1.5, placeholders until step 4), and the not-bore rule now requires the edge mean under 10 percent.  Trench allowed on 51.7% of corridor footage under `place_pavement_soil`.

## Permitting authority (new, FiberBid RoadAuthority join)

- `RoadAuthority` bbox read: 81,876 HPMS 2024 segments in 10.97 s; classes {'state_dot': 38270, 'municipal': 24793, 'county': 13967, 'private': 2846, 'unknown': 1177, 'other_public': 565, 'federal_agency': 258}; confidence {'rule_verified': 77030, 'inferred': 3669, 'unknown': 1177}.
- Join: nearest segment within 30 m at 25, 50 and 75 percent of each edge; **72,915 of 80,063 edges matched, 92.6% of footage** (6.44 s).  Unmatched footage takes municipal inside a place, else county.
- Corridor footage by permit class: county 35,480,873 ft, municipal 25,893,993 ft, state_dot 15,588,981 ft, interstate 4,367,523 ft, federal_or_tribal 321,245 ft.
- Top authorities by footage: Nashville-Davidson metropolitan government (balance) 13,450,292 ft, 3 5,503,883 ft, Robertson County 3,500,755 ft, Spencer County 3,170,649 ft, Ohio County 2,847,425 ft, Logan County 2,596,611 ft, Daviess County 2,544,699 ft, Cheatham County 2,269,244 ft.

## Crossings (new: NHD water, FRA rail, FEMA floodway, USACE navigable)

- NHD (IN, KY, TN): 1,329 water polygons ({'LakePond': 971, 'Reservoir': 298, 'StreamRiver': 59, 'CanalDitch': 1}) and 66,456 flowlines ({'intermittent': 28924, 'perennial': 15420, 'artificial path': 15416, 'canal/ditch': 6696}) in the bbox, read in 4.92 s.
- FRA grade crossings in the bbox: 1218 ({'At Grade': 925, 'RR Under': 170, 'RR Over': 123}).  FEMA floodway polygons: 496 of 44,493 flood zone polygons.  USACE navigable waterway links: 19 (CUMBERLAND RIVER 7, GREEN RIVER 7, OHIO RIVER 5).
- Detection on all 80,063 edges in 31.9 s: crossings by kind {'dry_bridge': 812, 'water': 3623, 'rail': 656}; edges with a crossing 4,979; edges with only minor (intermittent, ephemeral, canal) flowline hits and no bridge, counted but not tiered: 5,355; floodway edges 2066, navigable edges 84, rail-over-road flags 76.
- Rules (assumptions `crossings`): polygon water on the edge: length = intersection ft (a bridge edge uses at least its own length); else a bridge edge over any flowline: length = bridge edge length; else a perennial flowline with no bridge: no_bridge_perennial_ft; minor (intermittent, ephemeral, canal) flowlines with no bridge are counted and flagged, not tiered, unless tier_minor_without_bridge is true.  Rail: At Grade: rail crossing of at_grade_ft on the nearest edge within join_max_m; RR Under (road bridge over rail): rail crossing of rr_under_ft (the bore under the tracks and the embankment, not the whole bridge; a 776 ft overpass at FM 1788 near Midland priced as Tier 2 rail before this, 2026-09-21); RR Over (rail bridge over the road): flag only.  Forced Tier 1: a water crossing within navigable_within_m of the USACE navigable waterway network is Tier 1 at any length (the Corps Section 10 rule). A water crossing on an edge inside a FEMA floodway polygon is Tier 1 when it is a real crossing of the floodway stream: polygon water or a bridge, at least floodway_min_ft long. A culvert-class default crossing of a side creek inside a wide floodway keeps its own tier (Ohio River bottoms finding, 2026-09-21).
- Priced at a tier across the whole graph: {'tier3': 4240, 'tier1': 43, 'tier2': 43} by tier, {'water': 3623, 'rail': 656, 'dry': 47} by kind.

## GeoTel carrier routes

- 62,999 features in the bbox in 0.59 s.  Named carriers found: ARELION, AT&T, COGENT, CROWN CASTLE, LUMEN, MOX, UNITI, VERIZON, ZAYO; not present: FIBERLIGHT, SEGRA.
- Corridor shared footage (within 250 ft of a named carrier): 17,162,334 ft (21.0%); by carrier AT&T 12,178,590 ft, LUMEN 3,279,812 ft, ZAYO 3,132,275 ft, UNITI 3,115,254 ft, VERIZON 2,354,511 ft, MOX 2,199,677 ft, CROWN CASTLE 991,457 ft, COGENT 813,511 ft, ARELION 639,843 ft.

## Timings (seconds)

| Step | Seconds |
|:--|--:|
| Assumptions build | 1.04 |
| Corridor total (store read plus graph build, or pickle load) | 1.48 |
| Places total | 2.18 |
| Soils total | 2.08 |
| Pavement total | 0.91 |
| Road authority total | 17.91 |
| Crossings total | 41.05 |
| Carriers total | 24.46 |
| Pricing | 0.71 |
| Spread (all solves and bookkeeping) | 2.9 |
| Dijkstra solves only | 2.832 |
| Route diversity | 0.054 |
| Shared segments | 0.52 |
| Comparison (human route) | 1.12 |
| Outputs (KMZ, HTML) | 1.66 |
| Total before the screenshot | 98.43 |

## Kept routes

Spread settings: penalty 1.3, overlap max 0.7, detour cap 1.35 times the shortest kept, max 20 routes, max 60 iterations.  20 solves, 20 kept, 0 pruned by the final cap.  R01 is the cheapest kept route.  Dollars are at this project's rates.

| Route | Miles | Dollars | $/ft | Diversity % | Shared ft | Longest shared run ft | Carriers (ft within 250 ft) | Crossing $ | Tiered crossings (water, rail, dry) | Tier 1 | Worst crossing | Permit $ | Trench ft | Bore ft | Metro ft | Inside place ft | county ft | state_dot ft | municipal ft | interstate ft | federal_or_tribal ft | Overlap vs R01 | secondary mi | residential mi | tertiary mi | primary mi | unclassified mi | trunk mi | motorway mi |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| R01 | 147.05 | $13,101,004 | 16.87 | 63.9% | 280,581 | 96,465 | AT&T 215,693; VERIZON 81,918; LUMEN 58,063; ZAYO 57,922; UNITI 42,166; CROWN CASTLE 18,847; MOX 3,342; COGENT 2,812 | $2,912,872 | 54 (44, 9, 1) | 3 | Tier 1 water 4,358 ft Ohio River; StreamRiver; artificial path on Owensboro Bridge $1,568,733 (forced Tier 1: USACE navigable waterway) | $230,045 | 504,485 | 271,944 | 418,935 | 196,023 | 174,367 | 523,138 | 77,937 | 215 | 772 | 100.0% | 15.0 | 12.3 | 48.6 | 11.7 | 9.9 | 49.5 | 0.0 |
| R02 | 155.78 | $12,865,731 | 15.64 | 80.4% | 160,961 | 48,412 | AT&T 110,244; LUMEN 62,310; ZAYO 41,598; UNITI 30,020; CROWN CASTLE 16,775; VERIZON 15,563; ARELION 5,848; MOX 1,543; COGENT 989 | $3,067,495 | 69 (64, 4, 1) | 3 | Tier 1 water 4,593 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,653,641 (forced Tier 1: USACE navigable waterway) | $307,797 | 588,592 | 233,909 | 289,855 | 141,976 | 325,433 | 377,533 | 78,127 | 39,836 | 1,572 | 0.6% | 52.3 | 41.0 | 22.5 | 13.0 | 14.9 | 4.6 | 7.5 |
| R03 | 151.41 | $13,670,820 | 17.10 | 53.8% | 369,417 | 70,857 | AT&T 282,116; UNITI 71,949; ZAYO 65,848; LUMEN 62,710; VERIZON 28,758; ARELION 11,150; CROWN CASTLE 8,945; COGENT 5,682; MOX 488 | $2,613,603 | 59 (52, 7, 0) | 3 | Tier 1 water 4,358 ft Ohio River; StreamRiver; artificial path on Owensboro Bridge $1,568,733 (forced Tier 1: USACE navigable waterway) | $369,852 | 458,851 | 340,609 | 370,767 | 216,160 | 200,369 | 426,125 | 131,848 | 39,545 | 1,572 | 0.7% | 26.7 | 37.7 | 14.6 | 48.1 | 13.3 | 3.6 | 7.4 |
| R04 | 156.98 | $13,987,076 | 16.87 | 70.9% | 240,814 | 50,514 | AT&T 189,185; UNITI 67,208; ZAYO 66,008; LUMEN 55,149; CROWN CASTLE 37,482; VERIZON 17,478; MOX 5,423; COGENT 3,090 | $3,521,017 | 75 (65, 9, 1) | 3 | Tier 1 water 4,593 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,653,641 (forced Tier 1: USACE navigable waterway) | $239,553 | 568,762 | 260,110 | 369,351 | 183,623 | 212,258 | 529,960 | 85,428 | 455 | 772 | 1.7% | 35.7 | 26.8 | 25.7 | 28.1 | 13.2 | 27.6 | 0.0 |
| R05 | 156.97 | $14,193,347 | 17.12 | 65.5% | 285,609 | 46,505 | AT&T 220,361; LUMEN 61,804; ZAYO 61,727; VERIZON 52,942; UNITI 52,183; CROWN CASTLE 15,231; COGENT 9,614; MOX 1,027 | $2,943,865 | 45 (38, 6, 1) | 3 | Tier 1 water 4,358 ft Ohio River; StreamRiver; artificial path on Owensboro Bridge $1,568,733 (forced Tier 1: USACE navigable waterway) | $235,839 | 512,594 | 316,222 | 368,082 | 264,197 | 210,138 | 537,662 | 80,240 | 0 | 775 | 11.6% | 42.8 | 26.9 | 29.3 | 35.9 | 8.9 | 13.2 | 0.0 |
| R06 | 156.80 | $14,362,443 | 17.35 | 68.7% | 258,776 | 79,264 | AT&T 231,957; UNITI 48,380; ZAYO 24,883; LUMEN 24,648; VERIZON 20,255; CROWN CASTLE 7,690; MOX 3,685; COGENT 1,071 | $3,403,620 | 71 (48, 22, 1) | 3 | Tier 1 water 4,588 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,651,511 (forced Tier 1: USACE navigable waterway) | $269,420 | 506,462 | 321,448 | 390,701 | 189,572 | 136,112 | 591,376 | 99,647 | 0 | 775 | 2.7% | 67.0 | 19.8 | 33.5 | 26.4 | 0.3 | 9.8 | 0.0 |
| R07 | 160.26 | $14,484,247 | 17.12 | 70.5% | 249,621 | 73,401 | AT&T 177,525; LUMEN 129,541; VERIZON 43,823; UNITI 39,022; CROWN CASTLE 34,362; ZAYO 27,790; ARELION 13,833; MOX 1,947; COGENT 982 | $3,240,113 | 65 (59, 5, 1) | 3 | Tier 1 water 4,588 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,651,511 (forced Tier 1: USACE navigable waterway) | $206,480 | 560,471 | 285,676 | 348,301 | 211,342 | 331,112 | 433,920 | 79,544 | 0 | 1,572 | 0.0% | 23.6 | 39.5 | 36.0 | 32.7 | 23.0 | 5.5 | 0.0 |
| R08 | 160.00 | $14,556,861 | 17.23 | 66.3% | 284,875 | 61,866 | AT&T 187,546; ZAYO 66,196; UNITI 38,516; VERIZON 25,069; LUMEN 24,506; MOX 20,237; CROWN CASTLE 1,885; ARELION 1,603; COGENT 1,019 | $3,315,593 | 52 (42, 9, 1) | 3 | Tier 1 water 4,358 ft Ohio River; StreamRiver; artificial path on Owensboro Bridge $1,568,733 (forced Tier 1: USACE navigable waterway) | $319,832 | 543,292 | 301,484 | 409,108 | 201,355 | 252,804 | 438,104 | 130,097 | 21,895 | 1,877 | 18.0% | 41.4 | 26.8 | 35.2 | 13.7 | 17.3 | 21.5 | 4.1 |
| R09 | 163.58 | $15,224,121 | 17.63 | 69.1% | 267,076 | 80,898 | AT&T 147,718; LUMEN 127,415; ZAYO 58,924; VERIZON 45,455; UNITI 38,275; MOX 16,410; ARELION 6,815; CROWN CASTLE 6,137; COGENT 4,137 | $3,313,037 | 58 (52, 5, 1) | 3 | Tier 1 water 4,593 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,653,641 (forced Tier 1: USACE navigable waterway) | $352,478 | 625,188 | 238,507 | 277,711 | 164,168 | 336,264 | 396,639 | 75,663 | 55,130 | 0 | 0.0% | 36.6 | 35.3 | 33.4 | 15.3 | 26.2 | 6.4 | 10.4 |
| R10 | 175.11 | $14,454,040 | 15.63 | 76.4% | 218,150 | 49,562 | AT&T 149,691; LUMEN 44,372; MOX 40,776; ZAYO 26,169; UNITI 15,828; VERIZON 10,681; COGENT 6,837; CROWN CASTLE 6,710 | $2,770,308 | 58 (53, 4, 1) | 3 | Tier 1 water 4,358 ft Ohio River; StreamRiver; artificial path on Owensboro Bridge $1,568,733 (forced Tier 1: USACE navigable waterway) | $417,977 | 672,660 | 251,928 | 294,178 | 181,884 | 402,909 | 350,248 | 95,899 | 75,531 | 0 | 2.2% | 33.9 | 52.8 | 37.4 | 17.6 | 18.8 | 0.3 | 14.2 |
| R11 | 171.87 | $14,941,398 | 16.47 | 65.4% | 313,977 | 63,046 | AT&T 284,474; UNITI 31,226; ZAYO 22,548; LUMEN 15,746; VERIZON 9,613; MOX 3,694; CROWN CASTLE 3,560; COGENT 2,002 | $3,610,822 | 69 (63, 5, 1) | 3 | Tier 1 water 4,588 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,651,511 (forced Tier 1: USACE navigable waterway) | $226,480 | 671,154 | 236,300 | 337,687 | 134,516 | 318,517 | 512,929 | 74,012 | 1,225 | 772 | 1.1% | 45.5 | 38.3 | 41.3 | 18.3 | 18.9 | 9.6 | 0.0 |
| R12 | 174.60 | $15,090,468 | 16.37 | 59.9% | 369,492 | 52,114 | AT&T 248,965; MOX 86,295; VERIZON 55,551; LUMEN 37,980; UNITI 29,751; ZAYO 25,226; CROWN CASTLE 17,240; COGENT 11,025 | $3,262,132 | 70 (64, 6, 0) | 3 | Tier 1 water 4,358 ft Ohio River; StreamRiver; artificial path on Owensboro Bridge $1,568,733 (forced Tier 1: USACE navigable waterway) | $447,794 | 652,030 | 269,864 | 432,795 | 192,662 | 374,952 | 405,344 | 46,953 | 94,644 | 0 | 17.2% | 27.2 | 31.8 | 28.9 | 25.0 | 28.5 | 15.4 | 17.9 |
| R13 | 179.89 | $15,380,631 | 16.19 | 77.7% | 211,403 | 44,079 | AT&T 144,646; MOX 76,422; LUMEN 43,000; VERIZON 32,190; ZAYO 16,529; UNITI 11,381; CROWN CASTLE 6,361; COGENT 3,832 | $2,537,973 | 74 (66, 8, 0) | 3 | Tier 1 water 2,728 ft Ohio River; StreamRiver; artificial path on Lincoln Trail Bridge $981,954 (forced Tier 1: USACE navigable waterway) | $441,521 | 723,928 | 225,899 | 285,438 | 186,684 | 290,343 | 532,554 | 47,159 | 79,771 | 0 | 1.0% | 56.6 | 23.6 | 55.1 | 6.9 | 20.7 | 2.0 | 15.0 |
| R14 | 173.22 | $16,688,772 | 18.25 | 78.8% | 193,779 | 25,502 | AT&T 170,045; UNITI 82,293; ZAYO 33,612; COGENT 5,070; MOX 4,736; VERIZON 4,400; LUMEN 2,628; CROWN CASTLE 498 | $3,895,891 | 69 (49, 17, 3) | 4 | Tier 1 water 4,588 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,651,511 (forced Tier 1: USACE navigable waterway) | $418,819 | 590,925 | 323,650 | 487,270 | 185,811 | 313,400 | 459,030 | 69,203 | 72,942 | 0 | 3.8% | 36.2 | 39.3 | 47.3 | 11.9 | 6.3 | 18.5 | 13.7 |
| R15 | 186.15 | $15,682,532 | 15.96 | 79.0% | 206,192 | 37,929 | AT&T 175,972; LUMEN 57,856; ZAYO 47,718; VERIZON 11,805; UNITI 8,183; ARELION 7,388; CROWN CASTLE 6,917; COGENT 5,352; MOX 546 | $2,439,474 | 79 (73, 6, 0) | 3 | Tier 1 water 2,728 ft Ohio River; StreamRiver; artificial path on Lincoln Trail Bridge $981,954 (forced Tier 1: USACE navigable waterway) | $260,047 | 737,535 | 245,346 | 268,717 | 205,739 | 388,847 | 474,738 | 114,410 | 3,314 | 1,572 | 0.0% | 39.5 | 65.0 | 37.0 | 19.8 | 24.0 | 0.4 | 0.4 |
| R16 | 177.56 | $16,742,614 | 17.86 | 77.5% | 211,142 | 34,235 | AT&T 182,488; LUMEN 51,952; VERIZON 34,045; ZAYO 18,593; UNITI 16,203; COGENT 3,089; MOX 1,880; CROWN CASTLE 526 | $3,305,376 | 71 (50, 18, 3) | 3 | Tier 1 water 4,588 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,651,511 (forced Tier 1: USACE navigable waterway) | $772,899 | 481,010 | 456,521 | 492,614 | 211,251 | 227,432 | 420,663 | 105,527 | 183,909 | 0 | 6.2% | 31.0 | 27.4 | 46.5 | 20.6 | 13.6 | 3.8 | 34.5 |
| R17 | 186.22 | $16,217,992 | 16.49 | 79.9% | 197,476 | 43,504 | AT&T 136,405; LUMEN 95,652; VERIZON 65,894; ZAYO 39,218; UNITI 19,106; CROWN CASTLE 13,777; COGENT 2,886; MOX 1,799 | $2,213,166 | 79 (73, 6, 0) | 3 | Tier 1 water 2,728 ft Ohio River; StreamRiver; artificial path on Lincoln Trail Bridge $981,954 (forced Tier 1: USACE navigable waterway) | $546,430 | 616,852 | 366,377 | 410,326 | 224,129 | 360,395 | 406,079 | 107,457 | 108,523 | 775 | 6.2% | 57.0 | 49.4 | 10.6 | 7.6 | 28.4 | 12.9 | 20.4 |
| R18 | 179.91 | $17,015,054 | 17.91 | 78.0% | 209,447 | 64,507 | AT&T 148,782; LUMEN 69,032; ZAYO 56,260; VERIZON 33,848; UNITI 32,393; CROWN CASTLE 18,003; COGENT 10,530; ARELION 4,111; MOX 3,615 | $3,846,623 | 73 (59, 13, 1) | 3 | Tier 1 water 4,593 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,653,641 (forced Tier 1: USACE navigable waterway) | $237,481 | 645,269 | 304,671 | 422,703 | 201,364 | 403,519 | 437,153 | 105,461 | 3,807 | 0 | 5.0% | 30.4 | 52.7 | 33.0 | 21.6 | 27.4 | 14.2 | 0.6 |
| R19 | 193.54 | $16,590,695 | 16.24 | 78.1% | 223,349 | 47,614 | AT&T 183,217; ZAYO 70,157; LUMEN 43,551; UNITI 29,383; VERIZON 14,645; COGENT 4,870; MOX 4,325; ARELION 2,782; CROWN CASTLE 1,887 | $2,690,780 | 69 (59, 10, 0) | 3 | Tier 1 water 2,728 ft Ohio River; StreamRiver; artificial path on Lincoln Trail Bridge $981,954 (forced Tier 1: USACE navigable waterway) | $273,958 | 760,128 | 261,763 | 328,774 | 204,768 | 380,573 | 532,615 | 100,922 | 7,781 | 0 | 0.0% | 50.3 | 61.8 | 35.2 | 19.0 | 20.3 | 5.7 | 1.4 |
| R20 | 159.11 | $20,151,177 | 23.99 | 70.6% | 247,236 | 124,107 | MOX 107,374; AT&T 82,441; LUMEN 78,704; VERIZON 59,219; ZAYO 23,823; UNITI 14,924; ARELION 6,689; CROWN CASTLE 4,037; COGENT 2,765 | $3,897,529 | 63 (55, 5, 3) | 3 | Tier 1 water 4,593 ft Ohio River; StreamRiver on William H. Natcher Bridge $1,653,641 (forced Tier 1: USACE navigable waterway) | $1,236,514 | 296,363 | 543,759 | 591,936 | 215,033 | 133,389 | 278,541 | 62,678 | 365,514 | 0 | 0.1% | 12.5 | 27.3 | 22.2 | 15.2 | 2.7 | 10.2 | 69.1 |

Soil footage per kept route (ft):

| Route | Soil 1 | Soil 2 | Soil 3 | Soil 4 | Soil 5 | Soil 6 | Soil 7 | Soil 9 | Soil 10 | Soil 11 | Soil 12 | Flagged ft |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| R01 | 11,914 | 359,226 | 82,816 | 7,272 | 220,949 | 284 | 86,027 | 0 | 3,463 | 350 | 4,129 | 3,779 |
| R02 | 3,561 | 439,156 | 63,248 | 5,388 | 215,772 | 997 | 89,171 | 100 | 3,815 | 0 | 1,292 | 1,292 |
| R03 | 4,844 | 416,343 | 79,196 | 10,192 | 187,726 | 0 | 91,782 | 0 | 3,150 | 642 | 5,583 | 5,589 |
| R04 | 3,561 | 391,816 | 47,745 | 43,234 | 232,516 | 1,453 | 93,429 | 0 | 4,778 | 10,341 | 0 | 10,612 |
| R05 | 18,956 | 331,437 | 100,041 | 8,690 | 263,945 | 2,372 | 86,608 | 0 | 3,637 | 0 | 13,130 | 12,477 |
| R06 | 3,554 | 350,647 | 103,573 | 14,890 | 271,807 | 4,277 | 70,520 | 0 | 4,615 | 0 | 4,028 | 3,844 |
| R07 | 3,554 | 442,786 | 66,907 | 15,461 | 191,962 | 2,345 | 116,812 | 2,145 | 3,726 | 299 | 149 | 442 |
| R08 | 14,862 | 345,252 | 106,945 | 15,286 | 263,855 | 2,746 | 85,620 | 647 | 3,923 | 0 | 5,641 | 5,238 |
| R09 | 3,561 | 399,056 | 74,864 | 6,697 | 237,580 | 1,351 | 135,419 | 1,298 | 3,868 | 0 | 0 | 49 |
| R10 | 2,591 | 484,027 | 68,183 | 16,814 | 216,731 | 9,387 | 115,832 | 847 | 3,483 | 0 | 6,693 | 6,199 |
| R11 | 3,554 | 345,493 | 87,297 | 36,683 | 319,141 | 4,659 | 106,076 | 0 | 3,952 | 0 | 598 | 592 |
| R12 | 1,945 | 436,135 | 91,297 | 40,495 | 240,111 | 964 | 104,092 | 100 | 3,662 | 1,565 | 1,528 | 2,696 |
| R13 | 5,984 | 462,386 | 55,677 | 18,007 | 202,977 | 14,919 | 186,042 | 0 | 2,773 | 566 | 496 | 471 |
| R14 | 3,554 | 359,596 | 125,351 | 9,790 | 291,311 | 5,213 | 113,807 | 0 | 4,297 | 0 | 1,655 | 1,850 |
| R15 | 4,572 | 496,823 | 55,768 | 10,298 | 198,816 | 18,384 | 195,023 | 0 | 2,309 | 0 | 888 | 392 |
| R16 | 446 | 488,060 | 114,053 | 11,976 | 215,057 | 1,390 | 102,216 | 98 | 4,234 | 0 | 0 | 50 |
| R17 | 2,127 | 455,297 | 92,142 | 18,551 | 248,106 | 15,681 | 143,490 | 0 | 4,539 | 698 | 2,599 | 4,595 |
| R18 | 3,561 | 403,086 | 54,222 | 45,434 | 300,659 | 0 | 139,017 | 0 | 3,960 | 0 | 0 | 49 |
| R19 | 32,994 | 416,908 | 99,620 | 13,022 | 251,201 | 32,863 | 171,380 | 0 | 2,901 | 0 | 1,003 | 926 |
| R20 | 446 | 446,915 | 75,234 | 13,519 | 130,015 | 5,480 | 158,786 | 3,793 | 3,779 | 0 | 2,155 | 2,126 |

Every crossing priced at a tier on the cheapest route (R01):

| Tier | Kind | Name | Road | Length ft | Dollars | Forced Tier 1 | Detection |
|:--|:--|:--|:--|--:|--:|:--|:--|
| tier1 | water | Ohio River; StreamRiver; artificial path | Owensboro Bridge | 4,358 | $1,568,733 | USACE navigable waterway | NHD polygon intersection |
| tier1 | water | Green River; Rough River; StreamRiver | US 431 | 1,645 | $592,120 | USACE navigable waterway | NHD polygon intersection (bridge length used, longer) |
| tier1 | water | Cumberland River; StreamRiver | Clarksville Pike | 772 | $277,763 | USACE navigable waterway | NHD polygon intersection (bridge length used, longer) |
| tier3 | dry | bridge over a minor flowline (intermittent) | SR 161 | 552 | $41,411 |  | OSM bridge edge over an intermittent, ephemeral or canal flowline: dry scale |
| tier3 | water | StreamRiver; Sulphur Fork Red River | North Main Street | 252 | $18,875 |  | NHD polygon intersection (bridge length used, longer) |
| tier3 | water | Rocky Creek; StreamRiver | US 431 | 237 | $17,776 |  | NHD polygon intersection (bridge length used, longer) |
| tier3 | water | Red River; StreamRiver | Dot-Tenn State Line Road | 225 | $16,847 |  | NHD polygon intersection (bridge length used, longer) |
| tier3 | water | StreamRiver; Sycamore Creek | Whites Creek Pike | 210 | $15,777 |  | NHD polygon intersection (bridge length used, longer) |
| tier3 | rail | CSX railroad at I-189 BY PASS (FRA 915010K) | Phillip Stone Way | 200 | $15,000 |  | FRA RR Under: road bridge over the railroad, bore under the tracks and embankment at rr_under_ft |
| tier3 | rail | CSX railroad at DEMONBREUN STREET (FRA 350198A) | Demonbreun Street | 200 | $15,000 |  | FRA RR Under: road bridge over the railroad, bore under the tracks and embankment at rr_under_ft |
| tier3 | water | StreamRiver; Wolf Lick Creek | Deerlick Road | 187 | $13,997 |  | NHD polygon intersection |
| tier3 | water | Bednigo Branch | Abednego Road | 166 | $12,448 |  | bridge edge over an NHD flowline |
| tier3 | water | Pond Creek | KY 2107 | 148 | $11,088 |  | bridge edge over an NHD flowline |
| tier3 | water | StreamRiver; Whites Creek | Tucker Road | 144 | $10,778 |  | NHD polygon intersection (bridge length used, longer) |
| tier3 | water | Carr Creek; StreamRiver | Tom Austin Highway | 128 | $9,619 |  | NHD polygon intersection |
| tier3 | water | Earthman Fork | Whites Creek Pike | 110 | $8,245 |  | bridge edge over an NHD flowline |
| tier3 | water | Panther Creek | Sutherland Road | 108 | $8,081 |  | bridge edge over an NHD flowline |
| tier3 | water | Bednigo Branch | Abednego Road | 106 | $7,955 |  | bridge edge over an NHD flowline |
| tier3 | rail | NS railroad at ROAD 350 NORTH (FRA 735852K) | East County Road 350 North | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | water | perennial | West County Road 200 North | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Huffman Ditch; perennial | North 200 West | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | South 200 West | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Garrett Creek | South 200 West | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Caney Creek | SR 161 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | rail | CSX railroad at J R MILLER BLVD (FRA 344251V) | J R Miller Boulevard | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | water | Buck Creek | US 431 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | US 431 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | US 431 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | rail | CSX railroad at W BROAD ST (FRA 347088L) | West Broad Street | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | water | perennial | KY 2107 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | KY 2107 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | John Prine Avenue | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Lazy Branch | US 431 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | Lewisburg Road | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Rawhide Creek | Lewisburg Road | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | Forgy Road | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | rail | RJCM railroad at FERGUSON RD (FRA 344519R) | KY 1151 | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | water | perennial | SR 161 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | US 41;US 431 | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | rail | CSX railroad at MAIN STREET (FRA 348124H) | South Main Street | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | water | Bednigo Branch | Abednego Road | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Earthman Fork | Whites Creek Pike | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | Whites Creek Pike | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | perennial | Whites Creek Pike | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | water | Dry Fork | Buena Vista Pike | 100 | $7,500 |  | perennial flowline, no bridge: culvert-class default length |
| tier3 | rail | CSX railroad at 16TH AVENUE NORTH (FRA 348015E) | 16th Avenue North | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | rail | NWR railroad at 16TH AVE NORTH (FRA 298467A) | 16th Avenue North | 100 | $7,500 |  | FRA At Grade: default rail crossing length |
| tier3 | water | Dry Fork; StreamRiver | KY 1151 | 91 | $6,859 |  | NHD polygon intersection |
| tier3 | water | Whippoorwill Creek | Gordonsville Road | 88 | $6,637 |  | bridge edge over an NHD flowline |
| tier3 | water | Whippoorwill Creek | Miles Road | 72 | $5,435 |  | bridge edge over an NHD flowline |
| tier3 | water | Elk Lick Creek; StreamRiver | Stuart Chapel Road | 58 | $4,313 |  | NHD polygon intersection |
| tier3 | water | Spring Creek | Dot Road | 53 | $3,993 |  | bridge edge over an NHD flowline |
| tier3 | water | Brush Fork | Abednego Road | 48 | $3,601 |  | bridge edge over an NHD flowline |
| tier3 | water | Bednigo Branch | Abednego Road | 40 | $3,021 |  | bridge edge over an NHD flowline |

Solve log (every iteration):

| Iter | Solve s | Miles | Dollars | Max overlap vs kept | Result |
|--:|--:|--:|--:|--:|:--|
| 1 | 0.115 | 147.05 | $13,101,004 | 0.0% | kept |
| 2 | 0.316 | 155.78 | $12,865,731 | 0.6% | kept |
| 3 | 0.086 | 151.41 | $13,670,820 | 4.8% | kept |
| 4 | 0.082 | 156.8 | $14,362,443 | 2.7% | kept |
| 5 | 0.081 | 156.98 | $13,987,076 | 7.7% | kept |
| 6 | 0.086 | 160.26 | $14,484,247 | 9.2% | kept |
| 7 | 0.311 | 156.97 | $14,193,347 | 11.6% | kept |
| 8 | 0.091 | 179.89 | $15,380,631 | 4.5% | kept |
| 9 | 0.095 | 163.58 | $15,224,121 | 10.7% | kept |
| 10 | 0.098 | 171.87 | $14,941,398 | 9.3% | kept |
| 11 | 0.094 | 175.11 | $14,454,040 | 16.8% | kept |
| 12 | 0.322 | 186.15 | $15,682,532 | 15.1% | kept |
| 13 | 0.094 | 160.0 | $14,556,861 | 24.0% | kept |
| 14 | 0.094 | 186.22 | $16,217,992 | 7.2% | kept |
| 15 | 0.099 | 159.11 | $20,151,177 | 7.0% | kept |
| 16 | 0.097 | 173.22 | $16,688,772 | 14.5% | kept |
| 17 | 0.328 | 174.6 | $15,090,468 | 17.2% | kept |
| 18 | 0.128 | 193.54 | $16,590,695 | 23.9% | kept |
| 19 | 0.113 | 179.91 | $17,015,054 | 12.7% | kept |
| 20 | 0.102 | 177.56 | $16,742,614 | 18.6% | kept |

## Comparison only, never a target: the human route and the bid, like for like

- The KMZ line was sampled every 50 ft (15,810 samples) for soils, places, pavement and the nearest HPMS segment; each sample took the OSM class and toll flag of the nearest corridor-graph sample point within 30 m (99.9% matched; the rest priced as unclassified county road).  Crossings on the human route are those of the 520 graph edges it runs along (796,028 ft of edges; an edge counts when at least 2 samples and 30 percent of its own sample count land on it).
- Inside-place footage 198,696 ft (Nashville-Davidson metropolitan government (balance) 107,198 ft, Springfield city 27,449 ft, Russellville city 23,650 ft, Coopertown town 12,300 ft, Lewisburg city 8,750 ft, Adairville city 8,350 ft); metro footage (pavement 10 percent or more) 310,794 ft; mean neighborhood pavement 13.3 percent (centerline cell 33.8); permit class footage state_dot 714,736 ft, municipal 43,699 ft, county 30,899 ft, interstate 600 ft, federal_or_tribal 550 ft.
- **Tool price of the human route at the bid's own rates: $15,780,565** (19.96 per ft): soil $11,917,069, crossings $3,606,296 (60 tiered: {'water': 53, 'dry': 3, 'rail': 4}, {'tier1': 3, 'tier2': 3, 'tier3': 54}), permitting adder $257,200; bore 377,343 ft, trench 413,142 ft.  At template defaults (base $12.00): $19,166,062.
- **Bid underground construction lines (footage times unit cost, `CONSTRUCTION LABOR BID` rows under the footage and unit cost headers, segment column H): $11,651,132 for 800,633 ft.**  trench 595,372 ft $5,730,690; bore 199,112 ft $3,706,442; crossing 6,150 ft $2,214,000.
- Plow convention: the tool prices every not-bore foot at the trench rate (Jeff, 2026-09-21).  The bid's plow lines repriced at this project's trench rates add $0, so the bid's own footage at the tool's convention is $11,651,132.
- **Ratios: tool over bid comparable 1.354; tool over bid-at-tool-convention 1.354; tool over construction labor K 0.705; tool over bid total P 0.395.**  Within 10 percent of the comparable underground number: no.  Footage: tool bore 377,343 ft (bid bore plus tiered crossings 205,262 ft), tool not-bore 413,142 ft (bid plow plus trench 595,372 ft); tool tiered crossing footage 18,431 ft $3,606,296 versus the bid's crossing lines $2,214,000.
- Bid presentation for this segment (row 9, SEGMENT 1: ROCKPORT, IN - NASHVILLE): LF 800,633, construction labor K $22,377,692, materials O $14,253,217, total P $39,921,733.  Construction labor also holds handholes, splicing, restoration, traffic control and the like, which the tool does not price.
- **Human route diversity: 52.8%**; shared 373,443 ft, near band 41,749 ft, longest continuous shared run 104,198 ft, most carriers on one stretch 6; by carrier AT&T 295,944 ft, LUMEN 102,448 ft, ZAYO 74,649 ft, VERIZON 63,399 ft, UNITI 54,349 ft, CROWN CASTLE 16,550 ft, COGENT 2,050 ft, MOX 1,600 ft.
- Cheapest tool route R01 versus the human route: 147.05 mi versus 149.71 mi (ratio 0.982); $13,101,004 versus $15,780,565 by the same model and rates (ratio 0.830); diversity 63.9% versus 52.8%.

| Soil class | Tool sample of the human line (ft) | Bid calculator soils block (ft) |
|--:|--:|--:|
| 1 | 3,350 | 134 |
| 2 | 346,043 | 362,426 |
| 3 | 58,299 | 47,201 |
| 4 | 32,849 | 29,556 |
| 5 | 237,495 | 234,088 |
| 6 | 1,000 | 6,536 |
| 7 | 96,098 | 84,141 |
| 9 | 0 | 1,042 |
| 10 | 4,400 | 4,470 |
| 11 | 10,350 | 17,500 |
| 12 | 600 | 13,539 |

Tiered crossings on the human route (from the graph edges it runs along):

| Tier | Kind | Name | Road | Length ft | Dollars | Forced Tier 1 |
|:--|:--|:--|:--|--:|--:|:--|
| tier1 | water | Ohio River; StreamRiver | William H. Natcher Bridge | 4,588 | $1,651,511 | USACE navigable waterway |
| tier1 | water | Green River; StreamRiver | US 62 | 1,843 | $663,503 | USACE navigable waterway |
| tier1 | water | Cumberland River; StreamRiver | Clarksville Pike | 775 | $278,963 | USACE navigable waterway |
| tier2 | water | perennial | US 231 | 997 | $149,550 |  |
| tier2 | water | perennial | US 231 | 698 | $104,732 |  |
| tier2 | water | Pup Creek | US 60;US 231 | 577 | $86,549 |  |
| tier3 | dry | bridge over a minor flowline (intermittent) | US 231 | 977 | $73,241 |  |
| tier3 | dry | bridge over a minor flowline (intermittent) | US 231 | 752 | $56,419 |  |
| tier3 | dry | bridge with no NHD water or FRA rail hit | US 231 | 712 | $53,404 |  |
| tier3 | water | South Fork Red River; StreamRiver | US 431 | 326 | $24,413 |  |
| tier3 | water | Red River; StreamRiver | Nashville Road | 318 | $23,863 |  |
| tier3 | water | StreamRiver; Sulphur Fork Red River | US 41;US 431 | 310 | $23,220 |  |
| tier3 | water | Rocky Creek; StreamRiver | US 431 | 237 | $17,776 |  |
| tier3 | water | Rough River; StreamRiver | North Main Street | 220 | $16,525 |  |
| tier3 | water | StreamRiver; Sycamore Creek | Whites Creek Pike | 210 | $15,777 |  |
| tier3 | water | South Fork Panther Creek | US 231 | 184 | $13,821 |  |
| tier3 | water | StreamRiver; artificial path | US 231 | 166 | $12,416 |  |
| tier3 | water | perennial | US 231 | 163 | $12,251 |  |
| tier3 | water | Lewis Creek | US Highway 62 West | 159 | $11,942 |  |
| tier3 | water | StreamRiver; Whites Creek | Tucker Road | 144 | $10,778 |  |
| tier3 | water | Pond Creek | Cr-1011 | 140 | $10,506 |  |
| tier3 | water | Muddy Creek | KY 69 | 137 | $10,261 |  |
| tier3 | water | Barnett Creek | US Highway 231 N | 132 | $9,884 |  |
| tier3 | water | Carr Creek; StreamRiver | Tom Austin Highway | 128 | $9,619 |  |
| tier3 | water | Earthman Fork | Whites Creek Pike | 110 | $8,245 |  |
| tier3 | water | StreamRiver; Wolf Lick Creek | Lewisburg Road | 104 | $7,767 |  |
| tier3 | water | Kelly Creek | US 60;US 231 | 100 | $7,500 |  |
| tier3 | rail | CSX railroad at WRIGHTS LANDING RD (FRA 344208P) | Wrights Landing Road | 100 | $7,500 |  |
| tier3 | water | Burnett Fork | KY 142 | 100 | $7,500 |  |
| tier3 | water | perennial | US Highway 231 N | 100 | $7,500 |  |
| tier3 | water | Little No Creek | US Highway 231 N | 100 | $7,500 |  |
| tier3 | water | perennial | US Highway 231 N | 100 | $7,500 |  |
| tier3 | water | No Creek | US Highway 231 N | 100 | $7,500 |  |
| tier3 | water | perennial | US Highway 231 N | 100 | $7,500 |  |
| tier3 | water | Bens Lick | KY 69 | 100 | $7,500 |  |
| tier3 | water | perennial | Rockport Lane | 100 | $7,500 |  |
| tier3 | water | perennial | Rockport Paradise Road | 100 | $7,500 |  |
| tier3 | water | perennial | Cr-1011 | 100 | $7,500 |  |
| tier3 | water | Daniel Run | KY 176 | 100 | $7,500 |  |
| tier3 | rail | CSX railroad at KY-176 (FRA 343388L) | KY 176 | 100 | $7,500 |  |
| tier3 | water | perennial | KY 176 | 100 | $7,500 |  |
| tier3 | water | Plum Creek | KY 176 | 100 | $7,500 |  |
| tier3 | water | perennial | John Prine Avenue | 100 | $7,500 |  |
| tier3 | water | Lazy Branch | US 431 | 100 | $7,500 |  |
| tier3 | water | perennial | Lewisburg Road | 100 | $7,500 |  |
| tier3 | water | Rawhide Creek | Lewisburg Road | 100 | $7,500 |  |
| tier3 | water | perennial | US 431 | 100 | $7,500 |  |
| tier3 | water | perennial | US 431 | 100 | $7,500 |  |
| tier3 | water | perennial | US 41;US 431 | 100 | $7,500 |  |
| tier3 | water | Black Branch | US 41;US 431 | 100 | $7,500 |  |
| tier3 | water | perennial | Memorial Boulevard | 100 | $7,500 |  |
| tier3 | water | Earthman Fork | Whites Creek Pike | 100 | $7,500 |  |
| tier3 | water | perennial | Whites Creek Pike | 100 | $7,500 |  |
| tier3 | water | perennial | Whites Creek Pike | 100 | $7,500 |  |
| tier3 | water | Dry Fork | Buena Vista Pike | 100 | $7,500 |  |
| tier3 | rail | CSX railroad at SEVENTEENTH AVENUE NORTH (FRA 348016L) | 17th Avenue North | 100 | $7,500 |  |
| tier3 | rail | NWR railroad at 17TH AVE NORTH (FRA 298466T) | 17th Avenue North | 99 | $7,424 |  |
| tier3 | water | perennial | US 41;US 431 | 96 | $7,200 |  |
| tier3 | water | perennial | KY 85 East | 70 | $5,233 |  |
| tier3 | water | North Fork Panther Creek | KY 142 | 60 | $4,503 |  |

## Still placeholder (all marked in assumptions_defaults.json)

- Metro multipliers (1.0, 1.15, 1.4, 2.0 by pavement bin) and permitting adders (county 0, state DOT 0.05, municipal 0.15, interstate 0.5, toll 0.75, federal or tribal 0.5, in multiples of dirt bore per foot) are Claude's placeholders until step 4 calibration.  The data behind them is now real.
- Crossing default lengths (perennial flowline with no bridge 100 ft, FRA at-grade rail 100 ft) and the rule that minor flowlines without a bridge are not tiered are Claude's interim choices; the tier rates and the calculator's three tiers are Jeff's.
- Soil classes 10, 11, 12 are priced as class 3 and their footage is reported as flagged.  Plow rows are unused; not-bore uses the trench multiples.
- Pipeline crossings (Big Springs priced 67,000 ft of them) have no data layer in the tool.

## What failed or was not checked

- Nothing failed in the run that produced this report (the report is written only after every step returned).
- Not checked: GeoTel positional accuracy; OSM bridge edges spanning the whole physical bridge; whether every FRA crossing sits within 30 m of its OSM road.
- The inside-place test uses the edge midpoint; the RoadAuthority join votes over three points per edge; the human line is tested per sample.
- The human route's crossings are taken from the graph edges it runs along, so a crossing on an edge the snap did not claim is missed, and its crossing footage is also priced once more as soil footage (small: 18,431 ft).

## Files

- `_Working\runs\rockport-nashville\routes.kmz`: one folder per kept route, A, Z, the human route (comparison only), shared segments, and tiered crossing points.
- `_Working\runs\rockport-nashville\explorer.html`: Leaflet map (routes, human route, shared segments, crossings), scatter, sortable table with permit and crossing columns, assumptions panel.  Needs internet for tiles and Leaflet.
- `_Working\runs\rockport-nashville\results.json`: every number in this report.  `bid_extract.json`: every bid line read, with cell addresses.  `run.log`: console log.
- `engine\projects\rockport-nashville\project.json` and `assumptions_overrides.json`.

- `_Working\runs\rockport-nashville\explorer-screenshot.png`: screenshot written (976,035 bytes) in 1.2 s; chrome exit 0.